全自動(dòng)丁基膠涂布機(jī)操作規(guī)程
時(shí)間:2024-12-14 來(lái)源:http://www.aabrs.cn/ 發(fā)布人:昌盛機(jī)械
全自動(dòng)丁基膠涂布機(jī)的操作規(guī)程主要包括開(kāi)機(jī)前的檢查和開(kāi)機(jī)后的操作步驟,以下是詳細(xì)的操作規(guī)程:
The operating procedures of the fully automatic butyl rubber coating machine mainly include pre startup inspection and post startup operation steps. The following are detailed operating procedures:
開(kāi)機(jī)前檢查
Check before startup
確保電源安全可靠,氣源壓力符合要求(0.6-0.8Mpa)。
Ensure the safety and reliability of the power supply, and ensure that the gas source pressure meets the requirements (0.6-0.8Mpa).
檢查電、氣路是否正常,各按鍵是否正常。
Check if the electrical and pneumatic circuits are normal, and if all buttons are functioning properly.
開(kāi)機(jī)操作步驟
Power on operation steps
接通電源、氣源。
Connect the power and gas sources.
將油缸升降開(kāi)關(guān)調(diào)至中位,啟動(dòng)液壓站。液壓站啟動(dòng)穩(wěn)定后,將油缸升降開(kāi)關(guān)轉(zhuǎn)至“升”位置,使膠缸活塞提起,離開(kāi)膠缸,返至最高位置(此動(dòng)作必須在膠缸加熱到需要的溫度后進(jìn)行)。
Adjust the oil cylinder lifting switch to the center position and start the hydraulic station. After the hydraulic station is started and stabilized, turn the oil cylinder lifting switch to the "up" position to lift the rubber cylinder piston, leave the rubber cylinder, and return to the highest position (this action must be performed after the rubber cylinder is heated to the required temperature).
將氣源總開(kāi)關(guān)旋至“通”位置(或向上拉出),然后向上拉動(dòng)擺動(dòng)操作手拉閥,擺缸氣缸將膠缸活塞向后擺動(dòng),讓開(kāi)膠缸口可投入膠錠。完成后,推回?cái)[缸氣閥,并關(guān)閉氣源總開(kāi)關(guān)。
Turn the main switch of the gas source to the "on" position (or pull it up), then pull the swing operation manual valve upwards. The swing cylinder will swing the rubber cylinder piston backwards, allowing the rubber cylinder port to be opened and the rubber ingot to be inserted. After completion, push back the swing cylinder valve and turn off the main air source switch.
將膠缸活塞對(duì)準(zhǔn)膠缸中心,打開(kāi)膠缸壓力開(kāi)關(guān),使活塞慢慢下壓進(jìn)行入膠。
Align the rubber cylinder piston with the center of the rubber cylinder, turn on the pressure switch of the rubber cylinder, and slowly press the piston down to enter the rubber.
調(diào)整擠膠頭間距(6-16mm),并確保間隔框(條)與小壓輪、擠膠嘴中心對(duì)中性。
Adjust the spacing between the extrusion heads (6-16mm) and ensure that the spacing frame (strip) is aligned with the center of the small pressure wheel and extrusion nozzle.
啟動(dòng)傳送帶,開(kāi)啟加熱開(kāi)關(guān)、油壓開(kāi)關(guān)、膠缸活塞開(kāi)關(guān)。
Start the conveyor belt, turn on the heating switch, oil pressure switch, and rubber cylinder piston switch.
調(diào)整壓噴定時(shí)器、停噴定時(shí)器、停壓定時(shí)器。
Adjust the spray timer, stop spray timer, and stop pressure timer.
將間隔框(條)置于傳送帶上,并用手壓著間隔框(條)隨傳送帶前進(jìn),保證完全壓附在傳送帶上。
Place the spacer frame (strip) on the conveyor belt and press it with your hand to move forward with the conveyor belt, ensuring complete adhesion to the conveyor belt.
關(guān)機(jī)操作步驟
Shutdown operation steps
作業(yè)完畢后,首先關(guān)掉溫控開(kāi)關(guān)、膠缸活塞開(kāi)關(guān)、油泵開(kāi)關(guān)。
After completing the homework, first turn off the temperature control switch, rubber cylinder piston switch, and oil pump switch.
關(guān)掉傳送帶開(kāi)關(guān)。
Turn off the conveyor belt switch.
關(guān)掉氣源和總電源。
Turn off the gas source and main power supply.
工藝要求
technological requirements
調(diào)整傳送帶速度(一般為4—17m/min)。
Adjust the conveyor belt speed (usually 4-17m/min).
設(shè)定擠膠座溫度(一般為120℃±25℃),設(shè)定膠缸溫度(一般為120℃±25℃)。
Set the extrusion seat temperature (usually 120 ℃± 25 ℃) and the glue cylinder temperature (usually 120 ℃± 25 ℃).
根據(jù)加工單要求調(diào)整擠頭間距,并確保間隔框與小壓輪、擠膠嘴中心對(duì)中性。
Adjust the spacing between the extrusion heads according to the processing order requirements, and ensure that the spacing frame is aligned with the center of the small pressure wheel and extrusion nozzle.
注意事項(xiàng)
matters needing attention
膠未加熱到需要溫度,不得啟動(dòng)液壓站。
Do not start the hydraulic station until the glue has been heated to the required temperature.
嚴(yán)禁主傳動(dòng)停下時(shí)調(diào)整速度。
It is strictly prohibited to adjust the speed when the main transmission is stopped.
溫度未降到40℃以下,嚴(yán)禁停止傳送系統(tǒng)。
It is strictly prohibited to stop the conveying system if the temperature has not dropped below 40 ℃.
遇到停電或緊急情況,使用木棒將傳送帶與擠膠座隔開(kāi)。
In case of power outage or emergency, use wooden sticks to separate the conveyor belt from the extrusion seat.
請(qǐng)嚴(yán)格按照上述操作規(guī)程進(jìn)行操作,以確保設(shè)備正常運(yùn)行及人身安全
Please strictly follow the above operating procedures to ensure the normal operation of the equipment and personal safety
本文由 全自動(dòng)丁基膠涂布機(jī) 友情奉獻(xiàn).更多有關(guān)的知識(shí)請(qǐng)點(diǎn)擊 http://www.aabrs.cn 真誠(chéng)的態(tài)度.為您提供為全面的服務(wù).更多有關(guān)的知識(shí)我們將會(huì)陸續(xù)向大家奉獻(xiàn).敬請(qǐng)期待.
This article is a friendly contribution from the fully automatic butyl rubber coating machine For more related knowledge, please click http://www.aabrs.cn Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Coming soon.
- 全自動(dòng)丁基膠涂布機(jī)操作規(guī)程 2024/12/14
- 丁基膠涂布機(jī)在使用的常見(jiàn)問(wèn)題 2024/12/13
- 雙組份打膠機(jī)如何調(diào)整滴膠量? 2024/12/09
- 中空玻璃生產(chǎn)線的磨損如何解決 2024/12/07
- 雙組份打膠機(jī)對(duì)于打膠工作完成很重要 2024/12/05
- 全自動(dòng)封膠線的工業(yè)自動(dòng)化設(shè)備介紹 2024/12/03
- 玻璃涂布機(jī)設(shè)備:設(shè)備存在的安全隱患 2024/11/25
- 中空玻璃加工設(shè)備:玻璃開(kāi)膠的應(yīng)急處理措施 2024/11/21
- 中空玻璃生產(chǎn)線:玻璃起霧怎么辦?昌盛為您解決! 2024/11/20
- 中空玻璃加工設(shè)備:選擇中空玻璃,創(chuàng)更舒適的環(huán)境 2024/11/18
產(chǎn)品分類(lèi)Product categories
聯(lián)系我們Contact us
- 咨詢熱線:0531-85717458 13705446998
- 公司地址: 山東省德州市齊河安頭鄉(xiāng)企巢工業(yè)園
- 掃碼聯(lián)系我們: